SHIRLEY WATER MAIN RELOCATION

PMI was contracted to relocate the City of Shirley water main due to deteriorating conditions of the existing pipe. PMI designed and provided construction administration services for the relocation of 1,150 linear feet of 6” waterline containing 500 linear feet of 12” HDPE directional bore. Valves, sampling stations, and connections were included with the design. Arkansas Department of Transportation (ArDOT) permits were obtained for the directional bore under Highway 9 and for the removal of the existing waterline from the Highway 9 bridge.