Hazardous Waste Landfill Construction

PMI was awarded a general contract to construct two new hazardous waste landfill cells.  The scope of work included a site specific health and safety plan, traffic control plan, stormwater pollution prevention plan, over 100,000 cubic yards of earthwork and clay liner, compaction and permeability testing, a dual layered HDPE liner system, 40,000 tons of gravel and over 6,000 feet of HDPE piping.  A 3D model and GPS equipment helped to complete this time sensitive project 30 days ahead of schedule.